Completed Projects
Sheraton Hotel, Culture and Congress Centre
-
Place
Ankara / TURKEY
-
Construction Area
1.755 m²
-
Start Date
January 2001
-
Finish Date
September 2003
Project: Controlling, Supervision and Monitoring of Prestressed Slabs and Static Calculations and Design of Prestressed Parts of the Structure for Sheraton Hotel, Culture and Congress Centre
Employer: Turser Tourism and Trade Ltd. Co.
Contractor: Nurol Engineering and Construction Inc.
Duration of the Consultant Agreement: 32 months
The Date of the Consultant Agreement: 11.01.2001
MANAGEMENT
- Technical Consulting
- Project Management
- Risk Management
- Evaluation of Extreme Loading Conditions
- Prep. of Operation and Maintenance Manuals
- Material and Equipment Testing
- GIS & GPS System Analysis
- Know-How Transfer
ENGINEERING
- Building Construction
- -Parking’s & High-rise Buildings
- -Industrial Buildings
- Bridges
- Tunnels
- Water & Digester Tanks & Silos
- Towers
GROUP
- Technical Assistance and Advisory Services
- Tendering and Evaluation
- Contract Administration
- Supervision of Construction
- Inspection of Equipments
- Quality and Cost Control
- Institutional and Financial Structuring